ConstructionBear

AIA Pay App Explained

G702 and G703 walked through with real numbers. Retainage, stored materials, and the line items that get rejected.

By Dov Cohen · Published · Updated

The AIA pay app is the most important document on a construction project, financially. It is also the one most likely to slow down because of formatting errors, math mistakes, or missing paperwork. This guide walks through the G702 cover and G703 continuation sheet line by line, with example numbers, so you can submit a pay app that actually gets paid on time.

What G702 and G703 Are

AIA G702 is the one-page cover sheet. It summarizes the contract sum, the work completed to date, retainage held, prior payments, and the current amount due. AIA G703 is the multi-page continuation sheet that backs up the G702 with line-by-line detail from the schedule of values.

Together they form the monthly Application for Payment, often called the "pay app." Most owners require pay apps on a fixed monthly schedule (e.g., the 25th of each month, paid by the 25th of the following month).

The Schedule of Values, Briefly

The schedule of values (SOV) is the line-item breakdown of the contract sum, agreed at the start of the project. A clean SOV has 25 to 80 lines for a mid-size commercial project, organized roughly by CSI division. Each line has a description and a scheduled value. The sum of all line scheduled values equals the contract sum.

Frontload the SOV at your peril. Some contractors front-load early lines (general conditions, mobilization) so they bill more in early months. Architects know this and will push back. Reasonable front-loading is fine; aggressive front-loading triggers SOV disputes.

Step by Step

  1. Update the schedule of values. The schedule of values (SOV) is the line-item breakdown of the contract sum. Every pay app starts by updating the percent complete for each SOV line. Walk the site or call the trade foremen for each line; do not estimate from the office.
  2. Roll up to the G703 continuation sheet. For each line: scheduled value, work completed this period, work completed previous periods, total completed, percent complete, balance to finish, retainage held. Math reconciles down each column.
  3. Add stored materials if allowed. Stored materials get a column on the G703. Document with delivery receipts, photos, insurance certificates, and (for off-site) bonded warehouse paperwork. Architects who cannot verify on site will reject.
  4. Apply retainage. Per the contract: typically 10% on the first half of the project, 5% after substantial completion. Retainage applies to work completed and stored materials, but the percentages can differ. Read your contract.
  5. Subtract previous payments. G702 cover line for "less previous payments" reconciles against the running owner ledger. If your number does not match the owner accounts payable, you will not get paid this cycle. Catch the discrepancy before submission.
  6. Attach lien waivers. Conditional waiver from the GC for the current payment. Final waivers from the subs for the prior payment received. Without these the owner cannot legally release funds in most states.
  7. Route through the architect. Architect signs G702 to certify the work is in place. Owner pays based on architect certification. If the architect disputes a completion percentage, settle that before resubmission, not after.

G703 Walkthrough with Real Numbers

Imagine a $4,820,000 commercial tenant improvement contract, in month 4. Three SOV lines from the G703:

ItemScheduled ValuePrior PeriodsThis PeriodStored Mat'lsTotal to Date%BalanceRetainage 10%
03 30 00 Concrete$280,000$252,000$28,000$0$280,000100%$0$28,000
05 12 00 Structural Steel$420,000$210,000$84,000$42,000$336,00080%$84,000$33,600
09 21 16 Gypsum Board$190,000$0$57,000$0$57,00030%$133,000$5,700

Across all 60 SOV lines this hypothetical project shows:

G702 Cover, Line by Line

  1. Original contract sum. $4,820,000.
  2. Net change by change orders. $87,420.
  3. Contract sum to date. Sum of 1 and 2. $4,907,420.
  4. Total completed and stored to date. From G703 column G. $1,820,000.
  5. Retainage. Calculated per contract terms. 10% on the first half. $182,000.
  6. Total earned less retainage. Line 4 minus line 5. $1,638,000.
  7. Less previous certificates for payment. Sum of all prior owner-certified pay apps. $1,402,000.
  8. Current payment due. Line 6 minus line 7. $236,000.
  9. Balance to finish, including retainage. Line 3 minus line 6. $3,269,420.

Retainage in Practice

Retainage rules vary by state and contract. Common patterns:

Always model retainage in the SOV up front; do not improvise it on a pay app.

Stored Materials

Owners often resist paying for stored materials because they cannot legally take title until installed. To get stored materials paid, you generally need:

Stored materials on the G703 should drop off in subsequent pay apps as installation proceeds. The total completed plus stored values cannot exceed the scheduled value of the line.

Lien Waivers

Lien waivers are not part of G702 or G703 but they are required attachments. Two flavors:

Sub waivers follow the same pattern but flow from sub to GC. Most states use specific statutory waiver forms. Use the right form for the state of the project.

Common Pay App Rejections

How AI Helps With Pay Apps in 2026

Pay apps are the second-most-templatable document on a construction project (after submittals). The mechanical work is significant and the formats are stable. What AI workflows actually do today:

What AI does not do (and should not): walk the site to verify completion percentages, judge whether stored materials are properly stored, or negotiate with the owner. ConstructionBear handles the mechanics and leaves the judgment to you. Get early access here.

Internal Links

External Reading

For longer-form essays on construction finance and contracts, see Builders Digest.

Frequently Asked Questions

What is an AIA pay app?
A monthly application for payment from the contractor to the owner. The standard form is AIA G702 (cover) plus G703 (continuation sheet). The G703 is the schedule of values broken out by line item with completion percentages and dollars billed.
What is the difference between G702 and G703?
G702 is the one-page cover with totals: contract sum, completed to date, retainage, less previous payments, current payment due. G703 is the continuation sheet showing every line item of the schedule of values with quantity completed, stored materials, retainage held, and total billed.
What is retainage?
A percentage (typically 5 to 10 percent) the owner withholds from each pay app and releases at substantial completion or after a punch list. Retainage protects the owner against incomplete or defective work.
Can I bill for stored materials?
Yes if the contract allows it. Stored materials are paid at cost (or specified percentage) once they are on site, paid for by the contractor, properly stored, and insured. Off-site stored materials require additional documentation (bonded warehouse, sub-bond, lien waiver).
How long does an owner have to pay a pay app?
Most contracts say 30 days from architect approval. State prompt-pay statutes set a hard floor (often 30 days plus interest after that). Federal jobs follow the Prompt Payment Act.
What gets a pay app rejected?
Math errors, billing for work not performed, missing lien waivers, missing stored materials documentation, completion percentages that disagree with the architect site visit, and stored materials that the architect cannot verify on site.
Can AI generate AIA pay apps?
Yes. ConstructionBear drafts G702 and G703 from a chat description plus an updated schedule of values, complete with retainage math, prior payment tracking, and lien waiver references. The numbers reconcile against the contract sum automatically.